| VAOIG: NEW VA
SOFTWARE EFFORT MAKING SAME OLD MISTAKES
VA's new FLITE software is mired in
the same mistakes made by developers of CoreFLS, the infamous
third of a billion dollar boondoggle.
by Larry Scott, VA Watchdog
dot Org
-------------------------
The VA's CoreFLS financial
software system was a complete failure.
And,
it only took about $342 million to figure that out.
So, the VA, scrapped CoreFLS and
set about with a system called FLITE.
You can find out more about
CoreFLS here ...
http://www.yourvabenefits.org/sessearc
h.php?q=CoreFLS&op=ph
You can find out more about
FLITE here ...
http://www.yourvabenefits.org/sess
earch.php?q=FLITE&op=ph
The question was asked:
Could the VA make the same mistakes with FLITE that they made with
CoreFLS?
The Government Accountability
Office (GAO) thought that was entirely possible and just a year
ago issued a report that said:
Until the department addresses
all of the findings, the likelihood is increased that the
problems experienced with CoreFLS could recur and jeopardize the
successful implementation of FLITE.
The GAO report is here ...
http://www.vawatchdog.org/08/nf0
8/nfsep08/nf092308-7.htm
Enter the VA's Office of
Inspector General (VAOIG) who just took a look at the progress of
the FLITE system and issued a report.

When the VAOIG says "have not
fully incorporated ... lessons learned" ... you know there are
problems.
The Summary of the VAOIG report
is below with link to full report.
-------------------------
Audit of FLITE Program
Management’s Implementation of Lessons Learned -- Report Number
09-01467-216, 9/16/2009 |
Summary |
Report (PDF)
The Office of Inspector General
conducted an audit to determine whether VA was effectively
managing the development of the Financial and Logistics Integrated
Technology Enterprise (FLITE) program.
FLITE program managers have not
fully incorporated Core Financial and Logistics System (CoreFLS)
lessons learned into the development of FLITE: program managers
need to take additional steps to improve program oversight.
As a result, issues similar to
those found during the implementation of CoreFLS have already
occurred within the FLITE program.
Critical FLITE program functions
were not fully staffed, non-FLITE expenditures were funded through
the FLITE program, and contract awards did not comply with
competition requirements.
This occurred because FLITE
program managers have not implemented management controls needed
to ensure that effective and efficient monitoring of the lessons
learned takes place.
They also were not taking
actions to ensure that the lessons learned were completed or
adequately resolved problems.
Without management’s attention
to address the issues identified, the program faces an increased
likelihood that mistakes made during CoreFLS will reoccur and
prevent the successful implementation of FLITE.
The Assistant Secretaries for
Information and Technology and Management; and the Executive
Director, Office of Acquisition, Logistics, and Construction
agreed with our findings and 11 recommendations and provided
acceptable implementation plans.
The Assistant Secretaries and
Executive Director have already implemented 7 of our 11
recommendations.
Implementing these
recommendations is expected to improve FLITE program managers’
oversight of the FLITE program, which in turn is expected to
increase the probability of FLITE’s success.
The planned actions for the
remaining four recommendations are acceptable.
Accordingly, we consider all
planned actions acceptable, and we will follow up on their
implementation until all proposed actions have been completed.
-------------------------
TOPICS:
veterans, veterans' benefits, VA, Department of Veterans' Affairs,
VAOIG, FLITE, CoreFLS |